Stay Up-to-Date with the Construction Progress at London2

Stay Up-to-Date with the Construction Progress at London2

With work continuing at pace on site, this week saw the start of the off-site factory testing of the key items of plant with a trip to Finland to test the UPS systems for the first data hall.

Written by Simon Anderson Published Tuesday, 08 July 2014 08:00

Another week, another Factory Acceptance Test. The LV panels for the UPS switchrooms and PDU’s for the Data Halls have been inspected and tested to ensure that they are ready for installation – with some sections weighing in excess of 2000kg, checking these before they are placed in position is essential to avoid any double handling. As with our LONDON1 site, we have branded and coloured the switchboards…